1-
Crane Hooking up and start lifting. The hull weighing 7 tons. |
5-
One small hand from one Caterpillar lifting to speed up the
operation. careful done to do not damage the hull. |
| |
2-At certain heights
wooden blocks are used to support the hull, then the rope is slid. the step
is repeated many times to make the hull rest over one side.
|
6-
Almost in upright position. |
| |
|
3- The hull was
completely laid down over the starboard side. |
7-Now,
placing the final wooden blocks to support the hull definitely. |
|
. |
4-One
time more the rope is slid |
8-Final
leveling transverse and longitudinal. |
| |
9- At the end after 3
work hours the hull is at upright position.
|
|
| |